You’ve put real work into getting here. You chose a contractor, settled the design, picked the tile and the vanity, and booked a start date. Now the crew is about to arrive, and a new question comes up: what will actually happen in your home, and when?
A typical bathroom renovation schedule runs five weeks from demo to final walkthrough. Week 1 is demolition and rough-in, week 2 is waterproofing and the start of tile, week 3 finishes tile and grout, week 4 brings in the finish trades, and week 5 is glass, a final check and handover.
Knowing the order of things takes a lot of the guesswork out of the next five weeks. When you can see the plan, you can arrange your household around it, know which trade is coming to the door, and stop wondering whether the job is on track. Here is how a typical five-week bathroom moves at JJ Legacy Contracting, for homeowners in Ancaster, Hamilton and the surrounding area.
How early should you start planning?
If you’re still early in the process, give yourself about three months before you want the crew to start. That leaves time to choose a contractor, finish the design, sort out any permits and order materials. When everything is in hand before demo day, the five weeks below can run on time.
What does a bathroom renovation schedule look like week by week?
Week 1: Demolition and rough-in
We protect your floors and the path to the bathroom, then take the room down to the studs. Framing and backing go in for the vanity, mirror, lights and shower fixtures. The plumber and electrician rough in the new locations, the exhaust fan is ducted all the way outside (as it is in every bathroom we build), and if your design includes a tub, it’s set now. By the end of the week, ESA has inspected the electrical rough-in and your project manager has done the first of three in-house inspections, all before any walls are closed.
Week 2: Waterproofing and the start of tile
The shower or tub area is built with the Schluter waterproofing system, and in-floor heat goes down if it’s part of your design. Drywall starts outside the wet area. Before a single tile is set, the shower is flood tested for 10 hours to prove it holds water. Your project manager does the second inspection, you approve the tile layout, and floor tile begins.
Week 3: Tile and grout
Wall tile goes up while drywall finishing runs alongside it. Once the drywall is sanded and primed, the tile is grouted, so sanding dust never settles into fresh grout. As soon as tile is complete, the shower glass is measured. Because the glass is custom made to those measurements, it takes about a week to arrive. This is the week the room starts to look like a bathroom again.
Week 4: Finish trades
Trim and paint go on, and the vanity and countertop are installed. The electrician returns for lights, the fan and the floor heat thermostat. The plumber connects the toilet, faucets and shower trim, and ESA completes its final inspection.
Week 5: Glass, final check and walkthrough
Your custom glass is installed. Your project manager does a final quality check, the crew handles any touch-ups, and the room gets a thorough clean. Then we walk through the finished space with you.
What is it like to live at home during a bathroom renovation?
Most homeowners stay in the house for the whole project. The bathroom is out of use for all five weeks, so if it’s your only full bath, it’s worth planning ahead for showers. There will be a few short stretches when the water to the house is off, usually during rough-in and when fixtures are connected, and we’ll let you know ahead of time. You’ll get daily updates in your client portal, so you always know which trade is coming next, and you’ll have one dedicated project manager to call with any question.
What can change a five-week timeline?
Larger bathrooms, structural changes or work outside the bathroom can stretch a project to about seven weeks, and we tell you that before we start. Buffer days are built into every schedule, so a surprise behind an old wall doesn’t automatically push back your finish date.
Five weeks later, the room is finished, checked at every stage and ready to use. It was built in the right order, the plan held, and your home is yours again.
If you’re still planning a bathroom in the Ancaster area, we’d love to talk through your project with you. Book a short call with JJ Legacy Contracting, and we’ll walk you through what your own schedule could look like.